1. Prepare preliminaries |
Before starting any sort of apartment renovation project, you need to confirm the following:
|
|
2. Phone consultation |
A member of our team will book in a phone consult to find out a bit more about your project such as:
Duration of call: 30 minutes |
|
3. Ballpark quotation |
A member of our team will send you a ballpark quotation for your review and approval. This includes:
Lead time for ballpark quote: 48 hours |
|
4. Onsite consultation |
We will book in an on-site consultation ($250 + GST) to discuss:
It’s also a great chance for you to raise any questions you may have regarding the build or design and to get a feel for Mr & Mrs Elias as your designer and builder. Duration of meeting: 60 minutes |
|
5. Sign works contract |
Our team will email you the final revised quotation and works E-contract (7 days after site visit) to sign and lock in a start date. After receiving this, we ask that you sign the E-contract so that we can begin work on your submission right away. Lead time for revised quote: 48 hours |
|
6. Engineering plans |
A member of our team and structural engineer will attend site to assess the integrity of walls required for removal. Lead time for engineering plans: 1 week |
|
7. Strata submission |
Our team will submit the following on your behalf;
Lead time for strata approval: 3-6 weeks |
|
8. Design and materials purchasing phase |
Whether you choose to do a construction only or design and construct arrangement, we will use the time during the strata approval to further outline the project.
Steps 7 and 8 can be switched if the project requires it. Lead time for design and materials purchasing: 3-6 weeks |
|
9. Approval and build |
Once we receive strata approval, we should have the design relatively refined and materials ordered and we will commence the exciting part; the build! |